Ancillary Files Page of the New Project Wizard
Use this page to select the rate, resource, calendar, and rolling wave calendar (optional) that will be used by the new project.
Contents
| Field | Description |
|---|---|
| Calendar | Click
|
| Rate | Click
|
| Resource | Click
|
| Rolling Wave Calendar | Click
The rolling wave calendar cannot be the same calendar that you specified in the Calendar field. While Cobra can facilitate earned value management on a weekly basis for the entire project, the data generated for long projects would be overwhelming. Rolling wave processing enables you to analyze earned value data in weekly periods for a defined window of time (for example, 1 month prior and 3 months after the status date), while retaining the rest of the data in monthly periods. This reduces the amount of data that you have to review. |
Parent Topic: New Project Wizard